Tables - documents required for grid connection purposes

In order to make it easier to gather all the documents required for the connection of a new consumption location, we have centralized for you one table for each required approval – location and TAC – use them as checklists. In case there is an x next to the document, you need it; in case there’s a dash, it does not apply in your case.

If you want to request a TAC for an existing consumption place (because the technical or administrative conditions for that specific place are going to change), you do not need a location approval (if the respective changes do not also involve the obtaining of a Building Permit), you only need to use the connection documentation table.

We have also included a table of the documents making up the user system file, which you will need towards the end of the connection process, before the connection certificate is issued. Request this fil from the certified company you have chosen and check, using the table, whether it includes all required information.